A4095 works - photo taken by David Olds

A4095 Road Works

You may have seen the matrix signs around Bicester warning of major works along the A4095 from 3 April.

SSE is starting work on Skimmingdish Lane at the electricity sub station on Monday 3 April for the installation of a new 33KV cable to supply the NW Bicester development.

Work will continue around the ring road with traffic lights,  finishing with a temporary closure of Howes Lane from 24 July until the end of October.

All work is expected to be complete by 29 October 2023.

For information, the permit reference is: LP701S30001317-02 and the road closure reference is T11484.